Gold from e-waste: 40,000 equivalent ounces describe planned capacity, not bullion already produced

Recovering metals from discarded devices is an industrial project, not a new gold quotation. On 18 November Modern Mining announced an 18-month plan for its first commercial-scale plant in North Carolina, designed for annual capacity of about 40,000 gold equivalent ounces.[1](https://modernmining.com/modern-mining-plans-its-first-commercial-scale-e-waste-gold-plant-with-capacity-for-about-40000-gold-equivalent-ounces-a-year-files-third-quarter-2026-financial-statements)
MINING.COM covered the project on 20 November and specifies gold equivalent ounces in the body, although its headline shortens the wording to gold ounces.[2](https://www.mining.com/modern-mining-targets-40000-gold-ounces-from-e-waste)

## Do not lose the unit in the headline
The company release describes recovery of gold, silver, copper and other metals through an aqueous-based process.[1](https://modernmining.com/modern-mining-plans-its-first-commercial-scale-e-waste-gold-plant-with-capacity-for-about-40000-gold-equivalent-ounces-a-year-files-third-quarter-2026-financial-statements)
Its capacity figure is expressed in gold equivalent ounces, not as 40,000 ounces of pure gold already delivered.[1](https://modernmining.com/modern-mining-plans-its-first-commercial-scale-e-waste-gold-plant-with-capacity-for-about-40000-gold-equivalent-ounces-a-year-files-third-quarter-2026-financial-statements)
We retain that original label rather than converting the total into tonnes of new bullion or guaranteed revenue.

## The demonstration facility and future plant are different stages
According to the company, its Greenville demonstration site has recovered and sold metal concentrate since November 2023 and settled 41 product lots between December 2023 and June 2026.[1](https://modernmining.com/modern-mining-plans-its-first-commercial-scale-e-waste-gold-plant-with-capacity-for-about-40000-gold-equivalent-ounces-a-year-files-third-quarter-2026-financial-statements)
The plan assigns plant construction, binding supply contracts and training to the first six to nine months, followed by commissioning and ramp-up during months nine to twelve.[1](https://modernmining.com/modern-mining-plans-its-first-commercial-scale-e-waste-gold-plant-with-capacity-for-about-40000-gold-equivalent-ounces-a-year-files-third-quarter-2026-financial-statements)
The pre-concentration plant’s design target is up to one tonne of waste printed circuit boards per hour: that measures material processed, not gold produced per hour.[1](https://modernmining.com/modern-mining-plans-its-first-commercial-scale-e-waste-gold-plant-with-capacity-for-about-40000-gold-equivalent-ounces-a-year-files-third-quarter-2026-financial-statements)
R2 certification is an objective to pursue, not an accreditation already obtained in the release.[1](https://modernmining.com/modern-mining-plans-its-first-commercial-scale-e-waste-gold-plant-with-capacity-for-about-40000-gold-equivalent-ounces-a-year-files-third-quarter-2026-financial-statements)

## A statistical recycling definition does not certify a plant
In its 3 November report definitions, the World Gold Council describes recycled gold as metal recovered from fabricated products and refined back into bullion; it excludes process scrap that never entered a finished product.[3](https://www.gold.org/goldhub/research/gold-demand-trends/gold-demand-trends-q3-2026/notes-definitions)
This helps distinguish post-use recovery from manufacturing scrap, but does not verify Modern Mining’s commercial capacity.[3](https://www.gold.org/goldhub/research/gold-demand-trends/gold-demand-trends-q3-2026/notes-definitions)
The company’s own release warns that feedstock availability, permits, costs and the ability to scale could prevent its targets from being reached.[1](https://modernmining.com/modern-mining-plans-its-first-commercial-scale-e-waste-gold-plant-with-capacity-for-about-40000-gold-equivalent-ounces-a-year-files-third-quarter-2026-financial-statements)
We do not treat the company’s proposed environmental or cost advantages as demonstrated. This is industrial reporting, with no price targets, purchase recommendations or personalised advice.